Churn Testing
No-flow tests on the weekly or monthly cadence required for your pump.

Fire Pumps & Standpipes
Weekly and monthly churn tests, annual flow tests, controller and driver service, and standpipe testing for high-rise and large-area buildings.
Overview
A fire pump boosts pressure so sprinklers and standpipes perform on upper floors and across large buildings. It may sit idle for years, which is exactly why it has to be tested on schedule.
We run no-flow (churn) tests, perform the annual flow test against the pump's rated curve, and service electric and diesel drivers, controllers and jockey pumps.

Churn, flow and controller testing.
What we do
01
No-flow tests on the weekly or monthly cadence required for your pump.
02
Measured flow and pressure plotted against the pump's rated performance.
03
Packing, bearings, couplings, relief valves and alignment.
04
Batteries, fuel, cooling system checks and exercise runs.
05
Hose valve inspections, five-year flow tests and dry standpipe hydrostatic tests.
06
Private hydrant inspections, flow tests and underground main flushing.
Standards & frequency
We build these intervals into your service calendar, so tasks happen on time and records are ready when your fire marshal or insurer asks.
| Test | Standard | Typical frequency |
|---|---|---|
| Fire pump no-flow (churn) test | NFPA 25 | Weekly or monthly, by driver type and building |
| Fire pump flow test | NFPA 25 | Annually |
| Standpipe flow test | NFPA 25 | Every 5 years |
| Dry standpipe hydrostatic test | NFPA 25 | Every 5 years |
| Private fire hydrants | NFPA 25 | Inspection and flow test annually |
| Underground mains | NFPA 25 | Flow test every 5 years |
Summary of commonly adopted NFPA 25 editions. Your adopted edition and AHJ determine actual requirements.
How it works
01
Nameplate data, original acceptance test and past results.
02
Weekly or monthly runs, logged every time.
03
Flow and pressure compared with the rated curve.
04
Corrections made and performance verified.
Questions
Have a question about your building? Call 218-262-9553 or send a request and a specialist will follow up.
NFPA 25 requires a no-flow test weekly for diesel pumps and, for most electric pumps, monthly. Some buildings, such as those where the pump is needed to meet demand beyond fire department capability, keep a weekly schedule. We confirm the requirement for your pump.
Water is flowed through a test header or flow meter at several points, and pressure and flow are compared with the pump's original performance. It shows whether the pump can still deliver what the system needs.
Building staff can run churn tests with training. We provide logs and walk your team through the procedure, and we handle the annual flow test and repairs.
Packing is designed to drip slightly to cool the shaft. Excessive leakage, or a dry and hot gland, needs adjustment. We check it at the next test, or sooner if it is severe.
Our 24/7 line connects you with an on-call coordinator who can dispatch a technician, help you plan fire watch, and document the impairment for your records.